Grading Plan Specifications for Small Sites

Stormwater Permits

There are three main permits associated with stormwater depending on the application. These permits cover industrial activities, municipal activities and construction activities. Within these categories, there are also two types of permits that may be issued associated with these activities, general permits and individual permits. Most activities are covered by general permits, however, some complex projects or facilities may require an indivudal permit. The permits are issued by the Arkansas Departement of Environmental Quality (ADEQ), however, some of the duties regarding approval are passed down from ADEQ to the cities. Tontitown is required to review and approve construction plans and issues a separate grading permit for these activites. Please reference the Tontitown Regulations tab for further information on grading permits. Below are links to the common general permits that are issued by ADEQ.

ADEQ Municipal General Permit

ADEQ Industrial General Permit

ADEQ Construction General Permit

Grading Permit Requirements

 

  1. Site Plan. Site plan at a scale no smaller than one inch equals 50 feet, showing property lines, vicinity map, north arrow, name of owner, developer, and adjacent property owners.
  2. Land to be Disturbed. Land areas to be disturbed shall be clearly identified.
  3. Streets and Rights-of-way. Location and names of all existing or platted streets or rights-of-way within or adjacent to tract and location of all utilities and easements within or adjacent to the property shall all be indicated.
  4. Structures. Location and dimension of existing structures.
  5. Natural Features. Location of natural features such as drainage ways, ponds, rock outcroppings and tree cover. Indication of 100 year floodplains as defined by FEMA.
  6. Acreage/Zoning. Total acreage and zoning classification.

The following items may be reported in text rather than shown on the grading plan.

 

  1. Time Schedule. A time schedule indicating the anticipated starting and completion dates and time of exposure of each area prior to stabilization measures.
  2. Fill Material/Compactions. Description of quantity (in cubic yards), source, and composition of imported fill material and compaction specifications. Note the quantity (in cubic yards) and destination of excavation materials to be removed from the site.
  3. Natural Vegetation Preservation. Proposals for preserving natural vegetation, including designating the area of preservation on the grading plan, and a description of evegetation or other permanent erosion control strategy. Measures for protecting trees targeted for preservation during land alteration activity.
  4. Runoff/sedimentation. Specification and details of measures to control runoff and sedimentation during construction indicating what will be used such as straw bales, silt dams, check dams, lateral hillside ditches, catch basins and the like; and construction entrance/exit.
  5. Dust. Where excessive dust may become a problem, a plan for spraying water on heavily traveled dirt areas shall be addressed.

Online Small Site Grading Permit

 

Tontitown GIS

gisTo access Tontitown's GIS data files for use in Google Earth. . .

CLICK HERE

Request Center

request24/7 Online Request Center... If you have a report, complaint or suggestion,

CLICK HERE

Pay Your Bill

epayYou can pay your water bill online safely by using our SOFTePAY system.

CLICK HERE

Go to top